Snapshot
Demolition of the George Hatch Building, S Block and multiple other structures.
Project Role
Subcontractor
What we did
Prior to commencement of the demolition works, a comprehensive hazardous material removal program was completed. Enclosures were constructed to ensure the safety of workers and hospital users.
Highlights
The staged works were conducted in the immediate vicinity of live hospital operations which required significant coordination to ensure hospital users were not impacted. Detailed manual separation works utilising mobile cranes were completed to safety isolate and secure the live hospital areas from the structures to be demolished.